The cost baseline is developed during which process?

  1. Perform integrated change control

  2. Estimate costs

  3. Develop schedule

  4. Determine budget

The correct answer is: Determine budget

The cost baseline is developed during the Determine Budget process. This process involves aggregating the estimated costs from the various activities and work packages to establish a cost baseline for measuring project performance. The other options are incorrect because A: Perform integrated change control is responsible for influencing the factors that create project changes and controlling changes to the project's scope, schedule, and costs. B: Estimate costs is responsible for developing an approximation of the monetary resources needed to complete project activities. C: Develop schedule is responsible for analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.